
Floor screed
Floor screed belongs to the finishing phase, the sixth in building a turnkey house: it is poured after the electrics, plumbing and underfloor heating, and tiling and final finishes follow. In Tbilisi, stroydom.ge prices cement-sand screed up to 50 mm at 28–42 ₾/m², plus 6–10 ₾/m² for each extra 10 mm. Semi-dry machine-laid screed with fibre is 32–48 ₾/m² from 50 m², and self-levelling 5–15 mm is 18–28 ₾/m². Screed over underfloor heating: electric from 95 ₾/m², water-based from 140 ₾/m². Removing old screed costs 15–25 ₾/m² and waterproofing 18–28 ₾/m². Two-year warranty, with handover after a flatness check of 2 mm over 2 m. We also take it as a standalone order from 1,000 ₾, but the main route is screed within a turnkey house.
We pour floor screed in Tbilisi in the finishing phase: after the electrics, plumbing and underfloor heating, and before tiling and final finishes. The scope covers base preparation, a perimeter expansion strip, waterproofing in bathrooms, fibre or mesh reinforcement, beacons set by laser, and pouring of cement-sand, semi-dry or self-levelling mix. How flat the layer is decides whether tile cracks and laminate creaks, so we accept screed with a straightedge check and record its moisture before handing over to the tilers.
You can order this job on its own
Orders start from 1,000 ₾. An engineer visits and measures free of charge, and we fix the estimate and schedule before work starts. We work in Tbilisi.
About the work
How does stroydom.ge deliver floor screed?
A floor flat to within 2 mm over 2 m, the base for tile, laminate and parquet, poured in the house after all the service routes are in.
What is included in floor screed?
Cement-sand screed
Traditional wet screed 30–80 mm thick with mesh reinforcement: reliable and cheap, but slow to dry.
Semi-dry screed
Machine-laid and pumped through a hose: fast, flat, with no risk of leaking to the flat below.
Self-levelling floors
Self-levelling compounds 5–15 mm thick under laminate, parquet and tile, used as the final levelling layer.
Screed with underfloor heating
Water or electric underfloor heating installed, pressure-tested and screeded over.
Stage of the house build · Phase 6 of 7: Finishing
At what stage of building a house is floor screed laid?
- 1Design and site preparation
- 2Groundworks and foundations
- 3Structural frame
- 4Roof and weathertight shell
- 5Building services
- 6Finishing
- 7External works
Floor screed is laid in the finishing phase, when the house is closed in with roof and windows and the services are installed. Electrical work, plumbing and underfloor heating are complete by then, because the screed covers all those routes laid in the floor. After the pour and strength gain, we hand over a flat, dry base for tiling and the final finishing works. In the schedule, screed comes after the services and before tiling and final finishes, so the finished floor never has to be opened up for pipes or cable.
On site we accept pressure-tested underfloor heating circuits and the completed wiring, set a single datum with a laser for the whole floor, and pour the mortar between beacons. In bathrooms, waterproofing is carried up the walls before the pour. In this order the pipes and cables are already in the floor, tile goes onto a flat surface, and the finishing materials land on a dry base.
What must be finished first
Before screeding starts, electrical work, plumbing and underfloor heating must be complete. Wiring is run in conduit across the slab, water supply and drainage are laid with outlets at the right points, and the heating circuits have passed a pressure test. We accept this work against a certificate: we check that every route lies below the future screed surface, that bathroom waterproofing is carried up the walls, and that the heating pipes are undamaged. If any line is unfinished, the pour waits: opening up finished screed for the services costs more than the screed itself.
What comes next
Tiling and the final finishing works follow the screed. We hand the tilers a base with a straightedge flatness measurement and a residual moisture record, because tile adhesive and laminate react to moisture in the screed differently. The finishing crews get flat floors with no thresholds between rooms, where doors hang without trimming. If tile is laid early on damp screed, the adhesive does not gain strength and the tile lifts. Screed cannot be poured after the final finishes either: wet mortar and dirt would spoil the finished surfaces.
Where does this work meet the neighbouring trades?
Plumbing in the screed
The plumbers bring the drainage and water supply through the slab before the pour. We check that the outlets are capped and sit below the screed level, and that bathroom waterproofing is carried up the walls. A pipe standing above the level gets damaged during floating, and the leak then shows up under the tile.
Underfloor heating pressure test
The underfloor heating is handed to us pressure-tested, with the pressure held for the whole pour. We record the gauge readings in the acceptance certificate and watch that the pipes do not shift as mortar is delivered. If the pressure drops during the work, the circuit is damaged, and fixing a leak under set screed means opening the floor.
Moisture before tiling
Tiling starts after the residual moisture of the screed has been measured with a meter. We hand the tilers a record with the readings so that the adhesive works on a dry base. If tiling begins on damp screed, water from the mortar rises into the adhesive, it does not bond, and the tile comes loose after the client has moved in.
Flatness for the finishes
The final finishes receive floors from us flat to 2 mm over 2 m, measured with a straightedge. On such a base doors hang without trimming and skirting sits without gaps. If the screed is poured with a level difference, the floor has to be levelled with adhesive or underlay beneath the finish, and the extra material goes on the estimate.
What is floor screed and why is it needed?
A floor screed is the levelling and load-spreading layer between the structural slab and the floor finish. In the finishing phase it comes after the services, because it covers every route in the floor: heating and water pipes, drainage, cable in conduit. If screed is poured earlier, it has to be opened up for the services and the monolithic layer loses its integrity.
For the same reason it is not laid until the house is closed in with roof and windows: rain and damp spoil the base and wet the mortar. Before tiling and final finishes the screed must gain strength and dry, otherwise tile adhesive will not bond and laminate will lift from residual moisture. The service life of the floor finish depends on the screed: with more than 2 mm of deviation over 2 m, porcelain tile flexes and cracks along the joints, while click laminate damages its locks and starts to creak.
The complaint usually lands on the tiler, though the cause sits two layers below. Beyond flatness, screed aligns levels between rooms with different finishes so there are no thresholds in the doorways, and acts as the heat-spreading layer over underfloor heating. We calculate thickness from the highest point of the slab, the diameter of the pipes laid, the cover over the heating circuit and the load the slab can take.
In Tbilisi we use three types: cement-sand (reliable, cheap, slow to dry), semi-dry machine-laid (fast, flat, minimal water) and self-levelling compounds as a finishing layer. The choice depends on the slab type, the schedule and what goes on top. Within a turnkey house, one crew does the screed under one estimate and one schedule: the services crews hand over finished, pressure-tested routes, we accept the work front, pour, and pass the floor to the tilers with a flatness and moisture record.
On a standalone order these interfaces fall to the client, who has to coordinate the schedules of several contractors and answer for what lies under the screed.
What stages does floor screed consist of?
Each stage runs only after the previous one is accepted — so hidden works are never "closed" before inspection, and a mistake never has to be hunted for through screed and plaster.
- 1
Survey and calculation
Laser survey of level differences across the whole area, a single datum for the entire flat or floor, and calculation of thickness and mortar volume. The datum is set once for the whole project, otherwise floor levels drift between rooms.
- 2
Base preparation
Removing old screed and debris, dust extraction, priming, filling cracks and junctions. On an unprimed base the mortar loses water downwards and never reaches full strength.
- 3
Expansion strip and waterproofing
Perimeter expansion strip and collars around columns; waterproofing in bathrooms and over wet rooms, carried 15–20 cm up the wall.
- 4
Underfloor heating (optional)
Mats or pipe laid at 100–200 mm spacing, fixed to the insulation, the circuit pressure-tested before pouring and kept under pressure throughout the pour.
- 5
Reinforcement
100×100 mm mesh within the screed or polypropylene fibre in the mix. Fibre cuts the risk of shrinkage cracking by 60–70%.
- 6
Beacons
Beacons set with a laser level at 1.5–2 m spacing. Beacons set off a string line drift by 5–7 mm, which is enough to ruin large-format tile.
- 7
Pouring
Mortar delivered, laid between beacons, struck off with a straightedge and power-floated. Work runs continuously within a room, because the joint between yesterday and today becomes a crack.
- 8
Curing and drying
Covered with film for 7 days, kept damp, left to reach the target moisture, and checked with a moisture meter before being handed over for the finish.
How does stroydom.ge control quality on site?
How we work on site — materials, equipment, tolerances, documentation and acceptance of hidden works.
Laser level
Beacons and the datum are set with a laser only, with a check measurement in every room.
Fibre reinforcement
Polypropylene fibre binds microcracks as the mix sets and reduces shrinkage cracking by 60–70%.
Moisture control
Before laminate or parquet we measure residual moisture with a meter (no more than 4% CM) and record the result in the act.
Perimeter strip
Always mandatory. Screed shrinks as it cures; without a compression gap it bears against the walls and cracks, usually at corners and doorways.
Semi-dry in occupied buildings
Less water means faster drying, less shrinkage and no risk of leaking to the floor below, which is often the deciding argument in an inhabited building.
What should be accounted for in Tbilisi and Georgia?
What we account for here: seismic intensity 8 (MSK-64), hot summers and damp winters, steep terrain, older stock with timber floors and worn city networks.
Timber floors
In the older stock of Sololaki, Avlabari and Mtatsminda the floors are timber and cannot carry 80–120 kg/m² of wet screed. We use dry floating floors or lightweight compounds after checking the joists.
Thickness over heating
At least 45 mm over a water pipe, 30 mm over an electric mat. Any less and the screed cracks from thermal cycling in the first heating season.
Seismic and movement joints
On large areas and in doorways we cut movement joints. A 12 m continuous screed slab with no joints will crack; the only question is where.
Drying times
Cement screed dries in 28 days, semi-dry in 7–14 days. Speeding it up with heaters is not allowed: an over-dried surface loses strength while water remains inside and later escapes into the finish.
Large level difference
Where the difference exceeds 8 cm we build up with compacted expanded clay, otherwise both cost and slab loading rise sharply.
Summer heat
In a Tbilisi summer at +35 °C screed loses water within hours and develops a network of cracks. We cover it with film immediately after floating and keep it damp for the first three days.
Screed before the services
If screed is poured before the electrics and plumbing are installed, the finished floor has to be chased for the services. Cuts appear in the monolith that reduce the strength of the layer, and flatness is hard to restore after such a repair. We therefore do not start pouring until we hold the acceptance certificate for the services.
Final finish on damp screed
When tile or laminate goes onto screed that has not dried, residual moisture is trapped under the finish. The adhesive loses grip, laminate swells, and mould can develop under tile. We therefore do not release the work front without a moisture record, even if the client is pressing for move-in.
How much does it cost and how long does it take?
Indicative price ranges in lari (₾) for standard conditions. The final estimate is fixed after measurements and specification approval.
| Item | What is included and the price |
|---|---|
| Cement-sand | Up to 50 mm: 28–42 ₾/m². Above that, plus 6–10 ₾/m² per additional 10 mm. |
| Semi-dry machine-laid | With fibre: 32–48 ₾/m² from 50 m². Below that area, bringing the equipment in is not economical. |
| Self-levelling floors | 5–15 mm under laminate and parquet: 18–28 ₾/m². |
| Screed with underfloor heating | Electric from 95 ₾/m², water-based from 140 ₾/m² including pressure test and manifold. |
| Base preparation | Removing old screed — 15–25 ₾/m², waterproofing — 18–28 ₾/m². |
| Terms | Advance no more than 15%, the balance by stages. 2-year warranty. Work is accepted with a 2 m straightedge flatness check and a moisture record. |
Updated:
Ready to estimate?
Leave a request — engineer site visit, measurement and a preliminary estimate for "floor screed" are free.

Need the “Floor screed” service?
Leave your phone number: we call back within an hour, clarify the scope and arrange a free site visit.
We will call within an hour, 24/7. You do not need drawings for the first conversation.
By submitting the form you agree to personal data processing. Privacy Policy
Frequently asked questions — Floor screed
Which is better: wet or semi-dry screed?
Semi-dry dries faster (7–14 days against 28), cannot leak to the neighbours below and shrinks less, so in occupied buildings we usually recommend it. Wet cement-sand screed is cheaper in materials and better for thin layers and complex geometry. Self-levelling compounds are not an alternative but a finishing layer on top of the screed.
How long before I can lay tile or laminate?
Tile can go down once the screed has gained strength and residual moisture no longer affects the adhesive: usually 14–21 days for semi-dry. Laminate and parquet need moisture no higher than 4% CM, which means 28 days for cement screed. Force-drying with heaters is not an option: the surface dries, water stays inside, and the finish lifts a month later.
Why does screed crack?
Three main reasons: no perimeter expansion strip (the screed bears against the walls and tears as it shrinks), drying too fast in a draught or under a heater, and a layer thinner than calculated without reinforcement. Fine surface shrinkage cracks are harmless; through cracks with separated edges mean that section has to be opened up and redone.
How thick must screed be over underfloor heating?
At least 45 mm above the pipe of a water circuit, otherwise the screed cracks from thermal movement. An electric mat needs 30 mm. The thickness is measured from the top of the pipe, not from the slab. This is the point most often forgotten when ceiling height is being saved.
Can screed be laid on a timber floor?
Ordinary cement screed, no. In the older stock of Sololaki, Avlabari and Mtatsminda the floors are timber and were never designed for 80–120 kg/m² of extra load. There we use dry floating floors on expanded clay fill or lightweight polymer-cement compounds, after checking the joists.
What if the floor level varies a lot?
Where the difference exceeds 8 cm, filling it all with mortar is expensive and heavy for the slab. We build up with compacted expanded clay and screed over it, or switch to adjustable joists. The choice follows the slab capacity and how much ceiling height can be given up.
Can screed be poured before the electrical and plumbing work is finished?
No. Screed covers every service route in the floor, so wiring, water supply and drainage must be installed and checked before the pour. If it is poured earlier, the finished floor has to be opened up to complete the services, which costs more than the screed itself and breaks the monolithic layer. In a turnkey house we accept the services against a certificate with a pressure test and only then start the pour.
What happens if tile is laid right after the screed is poured?
The tile comes loose. Adhesive does not bond on a damp base, and residual moisture from the screed rises into the adhesive layer and destroys the bond. That is why we hand the work front to the tilers only after a meter reading and once the screed has gained strength. The turnkey schedule has a set curing pause between screed and tile, and it cannot be shortened even when time is tight.
How does screed on a standalone order differ from screed within a house?
Within a turnkey house, screed sits in the overall estimate and schedule, the services are handed over to us against a certificate, and we pass the base to the tilers with a record. On a standalone order you agree the timing with the electricians and plumbers yourself, accept their work, and answer for what is left under the screed. The risk at the interfaces falls on the client.
Why is screed not poured at shell stage, when the slabs are already done?
While the house is open, rain and damp reach the base, and the mortar takes up extra moisture and dries unevenly. The services are also not laid yet, so a poured floor would have to be opened up. Screed therefore comes after the roof, windows and services, and we hand over the floor with a moisture record confirming it is ready for tile and the final works.




