
Electrical works
Electrical work in a house belongs to the services stage: after the roof and windows are in and the building is closed, and before screed and plaster. stroydom.ge designs and installs it in Tbilisi as part of a turnkey house or as a standalone order from 1,000 ₾. A complete point (socket, switch or light with cable) costs 55–85 ₾. A board of 12–24 modules is 600–1200 ₾, 36–54 modules 1500–2800 ₾. LSZH cable 3×2.5 is 8–12 ₾/m, an internet or TV outlet 45–70 ₾. A 60 m² flat with design, board and about 50 points comes to 6500–11000 ₾ over 2–3 weeks. Advance no more than 15%, prices fixed once the design is agreed.
We design and install electrical systems for houses, flats and commercial premises: load calculations, board schematics, cabling, board assembly with breakers and RCDs, accessory fitting and commissioning with measurements. In a house the work comes in two visits. First fix sits between the closed envelope (Roofing, Windows and glazing) and Floor screed, second fix follows Interior finishing. Low-voltage routes for Smart home and low-voltage follow the same design but run apart from the power cables. A mistake in the electrics is a direct fire risk, so we do not bend the standards even to save the client money.
You can order this job on its own
Orders start from 1,000 ₾. An engineer visits and measures free of charge, and we fix the estimate and schedule before work starts. We work in Tbilisi.
About the work
How does stroydom.ge deliver electrical works?
First fix goes in after the roof and windows and before screed and plaster; accessories go on after painting. What is buried in walls and screed cannot be redone without stripping the finishes.
What is included in electrical works?
Stage of the house build · Phase 5 of 7: Building services
At what stage of building a house is the electrical work done?
- 1Design and site preparation
- 2Groundworks and foundations
- 3Structural frame
- 4Roof and weathertight shell
- 5Building services
- 6Finishing
- 7External works
Electrical work is done at the services stage: once the frame is up, the roof is closed and the windows are in, but screed and plaster have not started. It comes in two visits. First fix: load calculations, chasing, back boxes, cable in conduit and board assembly. Second fix: sockets, switches, luminaires and commissioning with measurements.
Screed, plastering and painting take place between the visits, which is why the first visit cannot be put off. The design and load calculation are ready before anyone goes on site, so the routes and the board position are known in advance. The electrician comes in once the roofers and window fitters have closed the envelope, and leaves with the routes run, the board in its recess and photographs of every chase. The next crews take over those routes and the schematic: screed, finishing and low-voltage.
What must be finished first
Before electrical installation starts, Roofing and Windows and glazing must be finished: the house is sheltered from rain and wind and the openings are glazed. Chases, back boxes and the board recess are cut in dry walls, and cable and protective gear must not get damp. The design is ready by then too: loads are calculated, the board schematic is drawn and socket positions are agreed against the furniture and appliance layout. Horizontal chases in load-bearing walls are forbidden, so routes along the ceiling and vertical drops are set in the design in advance. If the roof or windows are late, the electrics wait rather than start early.
What comes next
After first fix the site passes to Floor screed: the screed is poured over cable that is already laid, so circuits in the floor, underfloor heating included, are inspected and photographed before the pour. Interior finishing follows: plaster covers the chases, then filling and painting. The electrician returns after painting, fits sockets, switches and luminaires, and measures insulation and earthing. Smart home and low-voltage runs alongside: its routes are laid to the same design, and its equipment connects to the finished board and supply.
Where does this work meet the neighbouring trades?
Roofing and windows
The electrician takes over a dry house: no leaks through the slabs, openings closed with windows. Comments on the roof and glazing are cleared before chasing. Otherwise moisture stays under the plaster together with the cable.
Floor screed
Screed covers floor cable for good. Before the pour we inspect the circuits in conduit, check routes against the plan, photograph them and seal the conduit against mortar. A line damaged during the pour is found only by opening the floor.
Plaster and painting
Plaster covers the chases, so back boxes are set to level and depth in advance and the board recess is left for its door. Accessories go on after painting: sockets fitted earlier pick up paint, and faceplates get scratched.
Low-voltage
Low-voltage routes for Smart home and low-voltage follow the same design but run apart from power. The electrician leaves space and supply for the low-voltage panel. Low-voltage ordered after the finishes ends up in surface trunking.
What is electrical works and why is it needed?
Electrics cannot be redone after moving in: the cable is buried in walls and screed, and reaching it means stripping the finishes throughout the house. A mistake here also means a risk of fire and electric shock. A modern home runs dozens of loads at once: oven, hob, dishwasher, washing machine, dryer, water heater, air conditioners, underfloor heating, car charger.
The combined demand easily exceeds 15 kW, and without a calculation those loads cannot be spread across circuits. So we calculate first and chase second. Heavy loads get dedicated circuits with their own breaker, wet areas get a 10 mA RCD, and the whole house gets a voltage relay, because voltage swings in Georgian networks are normal.
Breakers are chosen so that a short circuit trips only the affected circuit. Every chase is photographed before filling, every core is labelled, and a schematic stays on the board door. Five years later, when someone wants to hang a cabinet or add a circuit, that schematic is worth more than the board itself.
The position in the build is set by the building envelope. Chasing and fitting the board belong in a dry, closed house, so first fix starts after Roofing and Windows and glazing. Later the cable gets covered: screed hides the circuits in the floor, plaster hides the chases in the walls.
If the order is broken, work just finished has to be demolished. Accessories go on last, after painting, otherwise the faceplates get dirty and scratched. When one contractor builds the house, the load calculation, board schematic and low-voltage routes come from one design, one estimate and one programme.
The electrician knows when the roofers and window fitters will finish, and screed is not poured until the cable has been inspected. One contractor answers for the joints between trades.
What stages does electrical works consist of?
Each stage runs only after the previous one is accepted — so hidden works are never "closed" before inspection, and a mistake never has to be hunted for through screed and plaster.
- 1
Load calculation
Power demand calculated, cable sizes and breaker ratings selected.
- 2
Design and board schematic
Single-line board schematic, wiring layout and material specification.
- 3
Chasing and routes
Laser setting out, chasing, drilling for back boxes and the board recess.
- 4
Cabling
LSZH cable in conduit, terminated in back boxes to the design.
- 5
Board assembly
DIN rails, main switch, voltage relay, RCBOs and RCDs installed and wired.
- 6
Accessories
After the finishes: sockets, switches, luminaires, dimmers, thermostats.
- 7
Commissioning
Insulation and earth resistance measured, RCDs tested, test records issued.
How does stroydom.ge control quality on site?
How we work on site — materials, equipment, tolerances, documentation and acceptance of hidden works.
Discrimination
A hierarchy of breakers: a fault trips only the affected circuit.
Earthing
Earth electrode, a dedicated protective conductor to every socket, supplementary bonding in bathrooms.
Data cabling
Cat6, coaxial and CCTV cable run alongside power with the required separation.
Labelling
Every core is labelled, and the board door carries the schematic and circuit list.
Documentation
As-built schematic, test records and equipment certificates.
What should be accounted for in Tbilisi and Georgia?
What we account for here: seismic intensity 8 (MSK-64), hot summers and damp winters, steep terrain, older stock with timber floors and worn city networks.
Unstable supply voltage
In Gldani and Varketili the supply swings between 180 and 250 V. We fit an ABB voltage relay and, where needed, a stabiliser.
Old aluminium
In Soviet-era blocks the riser wiring is aluminium. We connect through crimped sleeves or WAGO connectors, never by twisting.
Seismic service entry
The incoming cable is left in a flexible loop with 300 mm of slack for ground movement, and the earth electrode is separate.
Underfloor heating
A dedicated 2.5 mm² circuit with an RCBO. LED lighting runs through dimmers rated for LED loads.
Data cabling and interference
Power and data run in separate chases 50 mm apart or crossing at 90°. Otherwise interference lands on the Cat6 and "the internet is slow" for no visible reason.
Chasing load-bearing walls
In concrete and panel buildings horizontal chases in load-bearing walls are forbidden because they cut structural rebar. We route along the ceiling with vertical drops, even where that is longer and dearer.
Chasing before windows
If walls are chased before the windows go in, open chases and back boxes take up moisture from the air and rain. It stays under the plaster and shows after painting. That is why the electrical programme is tied to the roof and window dates.
Changing the layout after chasing
Moving a socket or circuit after chasing means a new chase in a finished wall. We agree furniture and appliance positions before setting out. Once the chases are filled we change the layout only against the drawings, so as not to hit laid cable.
How much does it cost and how long does it take?
Indicative price ranges in lari (₾) for standard conditions. The final estimate is fixed after measurements and specification approval.
| Item | What is included and the price |
|---|---|
| Per point | Socket, switch or light point including cable: 55–85 ₾ per point. |
| Distribution board | 12–24 modules — 600–1200 ₾, 36–54 modules — 1500–2800 ₾. |
| Cable | LSZH 3×2.5 — 8–12 ₾/m, 3×4 — 12–16 ₾/m. |
| Data | Internet/TV outlet — 45–70 ₾, Cat6 installation — 6–9 ₾/m. |
| Flat, complete | 60 m² with design, board and about 50 points: 6500–11,000 ₾ over 2–3 weeks. |
| Terms | Prices are fixed once the design is agreed. Advance no more than 15%, the balance by stages. |
Updated:
Ready to estimate?
Leave a request — engineer site visit, measurement and a preliminary estimate for "electrical works" are free.

Need the “Electrical works” service?
Leave your phone number: we call back within an hour, clarify the scope and arrange a free site visit.
We will call within an hour, 24/7. You do not need drawings for the first conversation.
By submitting the form you agree to personal data processing. Privacy Policy
Frequently asked questions — Electrical works
How many sockets does a flat or house need?
It is calculated from use, not habit. A living room needs 6–8 points, a kitchen 12–16 with dedicated circuits for the oven, hob and dishwasher, a bathroom 3–4 with a 10 mA RCD. A missing socket later becomes an extension lead, and an extension lead under a rug is the most common domestic cause of fire.
What is an RCD and how does it differ from a breaker?
A breaker protects the cable from overload and short circuit; that is, it protects property. An RCD detects current leaking to earth and protects people: it trips if current passes through a body, where a breaker would not react at all. Wet areas get a 10 mA RCD, other circuits 30 mA.
Why is a voltage relay necessary?
In Gldani, Varketili and parts of Tbilisi the supply swings between 180 and 250 V. A relay disconnects the supply outside the safe band and reconnects after a delay. It costs 120–250 ₾ and protects every appliance in the house, while one burnt-out fridge costs more.
Can electrical work be done without a design?
Technically yes, practically no. Without load calculations you cannot choose cable sizes or breaker ratings, and without a wiring plan you cannot later hang a shelf without hitting a cable. We produce a single-line board schematic and a route plan, photograph every chase before it is filled, and hand the as-built schematic to the client.
What should be done with old aluminium wiring?
Aluminium in Tbilisi’s older stock is brittle, oxidises and was never rated for modern loads. Inside the flat we replace it entirely with copper. Where the riser stays aluminium, we make the joint with crimped sleeves or WAGO connectors with paste, because twisting copper to aluminium directly overheats and fails within a year or two.
How long does the electrical work take in a 60 m² flat?
Two to three weeks: a week of chasing and cabling, a few days to build the board, then a pause until the finishes are done and a final visit to fit accessories and commission the system. Accessories go on last, after painting. Otherwise, the faceplates get dirty and scratched.
When in the build does the electrician come?
Twice. First after the roof and windows, before screed and plaster: the house must be closed and dry with the walls still open. Second after painting, to fit sockets, switches and luminaires and take measurements. Earlier is impossible because of damp, later is too late: screed and plaster cover the cable.
Can walls be chased before the windows are installed?
No. Without windows, moisture gets into the walls and back boxes, while cable and protective gear are left unprotected. Damp plaster later shows stains and flaking. If the windows are late, it is better to move the electrics than to chase an open house and redo the finishes afterwards.
What is checked before the screed is poured?
Every circuit in the floor: the conduit is intact, the routes match the plan, the cores are labelled and the routes are photographed. The underfloor heating circuit is inspected separately, with its RCBO. Screed covers the cable for good, so the inspection happens before the pour, not after.
How does electrical work inside a house project differ from a standalone order?
The scope and standards are the same; the difference is who answers for the joints. In a house project the design, routes and low-voltage work to one programme, and we carry out the inspection before the screed ourselves. With a standalone order, coordination with the roofers, window fitters and screed stays with the client.




